Project Calendar

Key milestones for the WSCIO-CCA1 project, covering company-level disclosures and project-specific verification events. All dates are presented as target windows to account for normal operational variability.

Key Terms

Crediting Period
A 5-year timeframe during which a project can generate carbon credits. At the end of each crediting period, projects undergo a renewal process to demonstrate continued eligibility for the next period. This project has three consecutive crediting periods spanning 2022-2037.
Validation — An independent assessment by a Validation and Verification Body (VVB) confirming that the project design, baseline, and methodology conform to the applicable standard (ISO 14064-2 / ICR / TGSM) before a crediting period begins.
Verification — An independent assessment by a VVB after project activities have occurred, auditing monitoring data and confirming that quantified emission reductions meet the requirements of the applicable standard (ISO 14064-2 / ICR / TGSM). Successful verification results in the issuance of Verified (Ex-Post) carbon credits.
Monitoring Period
A specified timeframe during which the project proponent collects and documents data on project activities and emission reductions. The monitoring report produced at the end of this period is submitted for verification — the step that results in Verified (Ex-Post) carbon credits.
Transition Finance Statement — Coming Soon
A yearly document outlining Theaus Global's financial obligations and how they have been fulfilled.

Reading This Calendar

Date Display Format

  • Standalone dates indicate Theaus Global submissions that do not require third-party consultation
  • Events requiring third-party consultation show a Start date and Target Completion date

Target Dates

  • Transition Finance Statement: First release by May 31, 2026; subsequent releases target by ~April 30 (~120 days after fiscal year end of Jan 1).
  • Monitoring Reports: Yearly activity concluding December 31, with reports targeting March 31 (~90 days after period end).
  • Validation: Occurs at crediting period renewal; target June 30 (~90 days after April 1st submission window opens).
  • Verification: Target ~90 days following the verification cut-off date. We intend to pursue annual verification, unless it is a renewal year (crediting period transition).
Recent Milestones
Project Start
April 1, 2022
Crediting Period 1 Validated
Apr 1, 2022 - Mar 31, 2027
Monitoring Period Complete
Apr 1, 2024 - Sep 30, 2025
Verification #1 Complete
January 14, 2026
Upcoming Events
May 31, 2026
Transition Finance Statement (FY2025)
Target ~March 31, 2027
Monitoring Report (MR-2026)
Apr 1, 2027
Crediting Period 2 Begins
Jun 30, 2027
Crediting Period 2 renewal + validation; verification of validated Ex-Ante credits from Crediting Period 1.

Public Calendar: 2026-2028

The following milestones represent publicly disclosed commitments and scheduled events. Windows are expressed as Target / Outside dates where applicable.

2026

Crediting Period 1

Verification Event #1 Complete

WSCIO-CCA1

3,035,608 gross credits verified covering April 1, 2022 - September 30, 2025. Joint validation and verification by Carbon Check (India) Private Limited.

CompletedJanuary 14, 2026

Transition Finance Statement (FY2025)

Company

Public disclosure of carbon credit sale proceeds allocation, published within 120 days of fiscal year-end.

TargetMay 31, 2026

ICR Listing — WSCIO-CCA2

WSCIO-CCA2

Listing on the International Carbon Registry for WSCIO-CCA2.

TargetQ1-Q2 2026

2027

Crediting Period 1 → 2 Transition

Crediting Period Renewal, Monitoring Reports, and Transition

WSCIO-CCA1
  • Crediting Period 1 ends March 31, 2027; Crediting Period 2 begins April 1, 2027.
  • Monitoring Report (MR-2026): Annual monitoring data covering January 1 – December 31, 2026. Target ~March 31, 2027.
  • Monitoring Report (MR-2027-Q1): End-of-period stub covering January 1 – March 31, 2027 (final 3 months of Crediting Period 1). Submitted as part of the renewal package.
  • Renewal and Validation: Crediting Period 2 validation submission, VVB review, and crediting period renewal.
  • Verification of Ex-Ante Credits: Verification of validated ex-ante credits (CRBNX) from Crediting Period 1, converting remaining ~1.88M credits to verified ex-post (CRBNC).
TargetApril 1 – June 30, 2027

Transition Finance Statement (FY2026)

Company

Public disclosure of carbon credit sale proceeds allocation, published within 120 days of fiscal year-end.

Target byApril 30, 2027

2028

Crediting Period 2

Monitoring Report (MR-2027-Q2-Q4)

WSCIO-CCA1

Start-of-period stub covering April 1 - December 31, 2027. First 9 months of Crediting Period 2.

Target~March 31, 2028

Transition Finance Statement (FY2027)

Company

Public disclosure of carbon credit sale proceeds allocation, published within 120 days of fiscal year-end.

Target byApril 30, 2028

Extended Calendar: 2029-2037

2029
Crediting Period 2
2030
Crediting Period 2
2031
Crediting Period 2
2032
Crediting Period 3
2033
Crediting Period 3
2034
Crediting Period 3
2035
Crediting Period 3
2036
Crediting Period 3
2037
Crediting Period 3
Transition Finance Statement
Monitoring Report
Crediting Period 3 Renewal

Crediting periods end March 31, 2037. Extended calendars will be published following successful renewals.

2038-2122

Long-term Monitoring & Periodic Renewals

Recurring Disclosures

DisclosureFrequencyDescription
Transition Finance StatementComing SoonAnnualPublic disclosure of carbon credit sale proceeds allocation, published within 120 days of fiscal year-end. Published even in years with no credit sales.
Stewardship FrameworkAnnualPublished only if amendments are made following annual Board review.
Project VerificationAt crediting period transitions/renewalsIndependent third-party verification of emission reductions by an ISO 14065:2020 accredited verification body.